SMED implementation: 80% reduction in changeover time
Frequent product changeovers on the production line caused long downtime: 45 minutes per changeover with 3 operators at once. This limited capacity and reduced the line's flexibility.
Through a structured SMED analysis, changeover actions were mapped out and split into internal and external steps. External steps were organised outside of downtime wherever possible, and the remaining steps were standardised in new work instructions.
Changeover time dropped from 45 to 10 minutes, needing just 1 operator instead of 3. This delivered significantly higher machine availability, more planning flexibility, and lower operational costs.