Projects & cases

An overview of projects where process optimisation and project leadership led to measurable, lasting results. Per case: the challenge, the approach and the result.

Philips, Drachten
โˆ’80% changeover time

SMED implementation: 80% reduction in changeover time

Role: Process Engineer
45 min โ†’ 10 min
Changeover time per switch
3 operators โ†’ 1 operator
Staffing per changeover
80%
Reduction in changeover time

Frequent product changeovers on the production line caused long downtime: 45 minutes per changeover with 3 operators at once. This limited capacity and reduced the line's flexibility.

Through a structured SMED analysis, changeover actions were mapped out and split into internal and external steps. External steps were organised outside of downtime wherever possible, and the remaining steps were standardised in new work instructions.

Changeover time dropped from 45 to 10 minutes, needing just 1 operator instead of 3. This delivered significantly higher machine availability, more planning flexibility, and lower operational costs.

SMEDLeanManufacturingOEE improvement
Philips, Drachten
โ†“ Product rejects

Reducing product rejects through inspection process re-analysis

Role: Process Engineer
โ‚ฌ0
Extra investment
Root cause analysis
Approach
Structurally lower rejects
Result

The inspection process for baby products had a level of product rejects whose underlying cause was unclear. Adjustments based on assumptions delivered insufficient results.

With a Six Sigma root cause analysis, the inspection steps and criteria were thoroughly re-analysed. Based on data, the actual causes of rejects were identified, after which targeted, practical adjustments were made to the process.

The adjustments led to a structural reduction in product rejects, without requiring extra investment: a lasting quality improvement embedded directly on the shop floor.

Quality analysisSix SigmaRoot Cause AnalysisProcess improvement
Sunningdale Tech Ltd, Riga
โœ“ Fully stable

Start-up & stabilisation of a 20-machine production line

Role: Project Leader
20
Machines
None
Production downtime
On schedule
Planning

After an international relocation, a full production line of 20 machines had to be started up and made stable at a new location in Riga, involving multiple international stakeholders and a tight deadline.

As project leader, full responsibility was taken for planning, coordination, and progress monitoring. The start-up was approached in phases, with close alignment between local and international teams and active stakeholder and change management.

The production line was delivered fully operationally stable, on schedule and without production downtime: from planning to a fully running line, without surprises along the way.

Project leadershipChange ManagementStakeholder managementProduction line start-up